A mold build schedule is only useful when each stage has defined entry criteria, exit criteria, required deliverables, and verifiable inspection or release records. Each milestone must be supported by specific evidence such as steel receiving records, electrode release status, machining inspection records, assembly dry-run checks, or T0 readiness confirmation, in accordance with the injection mold validation guide.
This guide shows sourcing teams and tooling engineers how to review design freeze, steel receipt, electrode release, machining, assembly dry-run, and T0 readiness gates. Each stage should be checked using auditable evidence instead of vague progress percentages to maintain total project control.
If a supplier reports “70% complete,” that is not a milestone. A usable tooling schedule should show completed work supported by actual deliverables—such as steel certificates, machining records, and cooling verification—identifying remaining critical-path risks to ensure true T0 readiness.
Use this page during supplier audits, weekly tooling meetings, and pre-T0 gate checks to identify schedule gaps before they become sampling delays, unplanned rework, or invalid trial results.